Transmission Line 345kV

If you’ve recently been contacted by Sharyland Utilities regarding the construction of a transmission line across your property, it is important that you act now! Landowners MUST intervene in order to have a say in the final route. There are multiple opportunities to influence the process, but to have the greatest impact you must start the process early and with an experienced team of professionals. Please contact us today to schedule a free, 30-minute consultation to learn more about how Braun & Gresham, PLLC can help protect your land.

Transmission Lines in the Routing Phase:

Stiles to Coates

  • PUC Docket #46726
  • Reagan county
  • 138-Kv line
  • 95-110 ft tall, concrete or steel monopole structures
  • 100 ft. right-of-way
  • Intervention deadline: March 3, 2017
  • CLICK HERE for the map of primary alternative routes
  • Waiting for final order (final route to be chosen)

Sale Ranch to Natural Dam

  • PUC Docket #45397
  • Application filed on 12/7/15
  • Martin and Howard counties
  • 138-Kv line
  • 95-110 ft tall monopole structure
  • 100 ft. right-of-way
  • Intervention deadline: January 19, 2016
  • Waiting for final order (final route to be chosen)

Tall City to Glass

  • PUC Docket #45308
  • Application filed on 11/17/15
  • Martin and Midland Counties
  • 138-Kv line
  • 95-110 ft height monopole structure
  • 100 ft. right-of-way
  • Map of alternative routes
  • Deadline to Intervene: December 28, 2015
  • Waiting for final order (final route to be chosen)

Previous Lines:

Antelope-Elk Energy Center to White River – Hale, Floyd counties